meeting. The county already has spent about
$256,000 on upgrades since 2011, Brown explained. Funds already are available for the
work, but another $986,000 would be needed to complete the project, she added. The
total expense of the work has been put at
$1,333,569.50.
If everything stays on the projected schedule,
Brown pointed out, the design should be complete this winter, with construction starting in
late 2014 and completed in the summer of 2015.
Page 67
On a motion by TDC member Tony Swain,
seconded by Ed Braunlich, the advisory board
recommended the County Commission utilize
a funding mechanism Commissioner Nora
Patterson — who is also the TDC chairwoman — broached on Sept. 6 to her fellow commissioners. About $800,000 will come from a
percentage of TDT funds that will be used in
the future to finance new capital projects and
events to increase visitors' overnight stays in
the county. The rest will come out of impact
Riders of all ages compete in events. Image courtesy Sarasota County